Archive for May, 2016

CSA’s – They’re a waste of time!

The government, and most of the private sector too, is very committed to reducing costs in the construction process. The thing is most of the effort, quite rightly, focuses on site performance and delivery. But has anyone looked recently at the estimating and pre-tender stage? And in particular the amount of time the estimating teams put in to following some ridiculous CSA documents.

Here’s a few recent examples of ones I’ve come across and the first one gave me the reason to write this.

Example 1

Contractor sends the usual information by email, attached are some innocuous looking attachments labelled as section 2, section 3 etc.

Open the section 2 document and it’s a schedule for that part of the contract works (the project is in phases, and by the way it’s a school refurbishment project), so far so good.

Start reading

Room G01, stripping out items, several of them over 3 pages, that’s a lot of items for a small room. Keep reading…..Room G02, stripping out items, several of them over 2 pages, that’s a lot of items. Keep reading…..Room G03, stripping out items, several of them over 3 pages, this is getting repetitive now. Keep reading……….Room G04, more of the same………..

IMG_0832

100 pages later I’ve reached the end of the stripping out section!

Now start all over again for the re-instatement works, room-by-room element in detail by element in detail until we get to page 224.

The END.

For section 2!

Then we have a repeat for sections 3, 4, 5, 6, 7, 8 and 9. A whopping 945 pages long!

The brief for the contractor price every single item in full on the CSA please otherwise we won’t consider your tender.

Our brief measure every single item out in the CSA in full in that order.

Now I’m all for keeping busy and working hard, but this is just beyond me as to why someone would want this…………….unless of course you have

a) a lazy consultant qs who cannot produce a cost plan in the first place for his client, and is therefore using the tender document from the contractors to work out what the client can afford or,

b) a consultant qs who quite simply does not comprehend the inordinate amount of work and effort required by the contractor to price such a document, or

c) please insert your own answer here

Example 2

Same story, contractor sends the usual information via a portal website this time, result much the same. Innocent looking information arrives. 5 sites this time in separate locations. Need I say more. Please price the same scope of works (all houses and flats of very similar nature) 5 times over please keeping the costs for all sites separate.

Example 3

I think you get the gist…………I could go on

 

The thing is how does the supply chain react when receiving such documents?

We all know the answer to that, as we aren’t exactly quiet right now are we?

 

 

Some things never change…

pexels-photo

Some things never change do they?

I was just looking back at some old postings and re-read with interest my thoughts on
‘time to tender’, and I really can’t believe that nothing much has changed, or has it…..

Probably, as back then I was referring mainly to cds and dvds.

Now they are a thing of the past too and its all shared files/folders and portals.

Was it only 5 years ago that I made those comments?

The thing is despite everyone’s best endeavours (like that phrase – well the legal boys do) we are still in much the same place. Well us on the receiving end of what is churned out by professional design teams that is.

You see there still is no standard way in which information is distributed, filed or catalogued on any project, let alone two projects that might even be the same!

Why can we not get our act together and issue things in a sensible and logical fashion?

Everytime I receive a link to a download I click to get the information wondering how long its going to take me to understand what I’ve been sent, let alone what might be missing.

Will BIM give us some form of structure, will the professional bodies get together and put some order to things. I just don’t see it………….. I’d just better get on with it I suppose and deal with……………it’s just that it’s such a waste of time and resource, and that’s what irks me!

If you’ve time take a look at the Government Construction Strategy document for 2011 that I referred to, and then look at the 2016 version. Apparently we are now going to make 33% savings as opposed to 20% savings!

 

 


Enter your email address to subscribe to this blog and receive notifications of new posts by email.

Join 57 other followers

About Me

I’m now the Managing Director of Mynott Associates Limited my own specialist measurement business. I’ve been in the industry all of my life since I left school. My first job was with Bovis Construction as a management trainee where I trained to become a quantity surveyor. I’ve worked for contractors all through my career, I am FRICS, FCIOB and MCIHT qualified and act as an RICS assessor. I’m also a keen Arsenal supporter having followed them from a young boy

For more information, please click on my photo.

My Tweets

RSS The Construction Index News