Archive for the 'two stage tendering' Category

Some things never change…

pexels-photo

Some things never change do they?

I was just looking back at some old postings and re-read with interest my thoughts on
‘time to tender’, and I really can’t believe that nothing much has changed, or has it…..

Probably, as back then I was referring mainly to cds and dvds.

Now they are a thing of the past too and its all shared files/folders and portals.

Was it only 5 years ago that I made those comments?

The thing is despite everyone’s best endeavours (like that phrase – well the legal boys do) we are still in much the same place. Well us on the receiving end of what is churned out by professional design teams that is.

You see there still is no standard way in which information is distributed, filed or catalogued on any project, let alone two projects that might even be the same!

Why can we not get our act together and issue things in a sensible and logical fashion?

Everytime I receive a link to a download I click to get the information wondering how long its going to take me to understand what I’ve been sent, let alone what might be missing.

Will BIM give us some form of structure, will the professional bodies get together and put some order to things. I just don’t see it………….. I’d just better get on with it I suppose and deal with……………it’s just that it’s such a waste of time and resource, and that’s what irks me!

If you’ve time take a look at the Government Construction Strategy document for 2011 that I referred to, and then look at the 2016 version. Apparently we are now going to make 33% savings as opposed to 20% savings!

 

 

Two stage tendering with a twist

Here’s a variation on a theme for two stage tenders………..

How many have you been used to the traditional way of two stage tendering, simply price the prelims and give a percentage for profit and overheads.

Two stage tendering

Well maybe no more.

How many of you have seen this, or variations on this of late? Two stage tender, first stage is for the usual priced aspects of prelims, overheads and the like but now here’s the twist….

A large element of the project is to be priced and fixed at the first stage.

Other elements are to be budget costs, although in reality a design does exist and is provided with the tender documents.

I’ve seen this twice in the last month having never seen this before.

What do you think to this, a good way forward?

Is this the start of clients being able to avoid getting the run around after months of negotiations with a contractor only to find their budget has been blown?

Or is it something Contractors will shun viewing it as a risk not worth entertaining in the current economic climate for them?

Oh and by the way it’s a design and build project too, but you guessed that anyway.


Enter your email address to subscribe to this blog and receive notifications of new posts by email.

Join 57 other followers

About Me

I’m now the Managing Director of Mynott Associates Limited my own specialist measurement business. I’ve been in the industry all of my life since I left school. My first job was with Bovis Construction as a management trainee where I trained to become a quantity surveyor. I’ve worked for contractors all through my career, I am FRICS, FCIOB and MCIHT qualified and act as an RICS assessor. I’m also a keen Arsenal supporter having followed them from a young boy

For more information, please click on my photo.

My Tweets

RSS The Construction Index News